8/8/2019 4:28:24 PM
Need contractor to finish filling out paperwork, traffic control and job value
8/22/2019 9:45:38 AM
~Signed Permit by contractor doing work (not general) - received
~Job value - Recived
~Traffic control if needed - Attach from ROW19-01160
~ Sub Contractor Sign-on Traffic - needed - attach from ROW19-01160
12/17/2019 3:04:42 PM
Per Developer they are no longer using Colo Civil - will have new contractor. Blanco is doing the wet utility work; emailed Blanco to determine if they will be taking this permit over as well. If so, will need new application.
12/17/2019 3:22:58 PM
Developer email indicates new contractor is Hogan. Need updated permit application submitted.
3/9/2021 2:13:49 PM
Per Feb. 23rd email from Emiley stating that the sections of concrete that did not meet the required strength at 28 days (4500 PSI) will need to be removed, replaced, and retested. Unfortunately, the City will not accept core test results in place of the failing tests. Updated permit status to issued so inspections could be scheduled.
4/14/2021 4:14:47 PM
Need to remove & replace sections of concrete that did not meet strength (test #8, #10) and all concrete stones that were cored; emailed info to Kirk. Put permit on hold until Hogan renews their municipal license.
4/22/2021 11:25:49 AM
License has been renewed. Removing hold
5/17/2021 10:56:47 AM
Project put into initial warranty 5/17/21; streets (Bob R.) signed off and approved for initial warranty on 5/12/21.
9/13/2023 10:52:09 AM
9/13/23 - City issued final acceptance for this project.