Notes:
3/9/2021 2:14:35 PM
Per February 23rd email from Emiley stating that the sections of concrete that did not meet the required strength at 28 days (4500 PSI) will need to be removed, replaced, and retested. Unfortunately, the City will not accept core test results in place of the failing tests. Set permit status of ROW19-01161 to issued so inspections can be scheduled.
5/17/2021 10:59:42 AM
Project put into initial warranty 5/17/21; will be up for final acceptance inspections on 2/17/23.
9/13/2023 10:45:48 AM
9/13/23 - City issued final acceptance for this project.