Notes:
4/19/2022 9:52:51 AM
Stop work order issued 4/19/22 for working without a permit. Main line installed and manholes S.S. Need permit and to schedule inspections. Need licensed general municipal contractor to sign permit, need approved traffic control plans (fees added to permit) and then all permit fees paid before we can schedule subsurface field meeting.
5/31/2022 12:28:22 PM
Per Jim G. proceed with scheduling subsurface field meeting. Per Jenny W. we will not hold up DEV on the TCP approval. Updated permit status to approved so permit can be paid for and scheduled subsurface field meeting for 6/2/22. Do not have permit forms, no approved TCP and no permit fees paid.
7/1/2022 8:36:39 AM
Permit forms submitted, and DEV permit fees paid to date. Per Jenny W./Jim G. can proceed without approved TCP. Set permit status to Under Construction.